Case Study

"It's great to see this information so clearly, so we can build with next steps!"

Advanced Manufacturing Director, sports and supercar OEM

Unblock engineering releases to prevent 2-3 months further slippage for an already late program, avoiding associated cost, revenue and reputational implications.

Outcomes

ECM processes

64

22

Engineering resource material cost savings

~£2.5M

Drawing checks

35%

58%

Time clawed back from projected launch delay

2 months

Engagement cost

£117k

A sports and supercar OEM was facing two to three months of further slippage on an already late program. We embedded a consulting team to unblock engineering releases, working alongside the client's Release and Purchase team to accelerate the pace of change.

Consulting

  • Governance with key stakeholders to align priorities and escalate blockers
  • Validation of the size of the task
  • Process mapping to identify constraints
  • Updated metrics
  • New support material

Release and Purchase team

  • Bottleneck elimination
  • Data visualisation
  • Prioritised change-management meetings
  • Effective escalation
  • Acceleration of change

Reach out to start a conversation

Every business faces unique challenges, and we're here to listen, not presume. Share your contact details, and one of our experts will reach out to discuss your specific needs. No spam, just tailored solutions.

Your information will be used in accordance with our privacy policy. Manage your subscription preferences.